A Rule I Was Taught Early
When I started out, I was told to run every project in the same order. Secure the land. Line up financing. Get permits. Then build. Do the steps out of order and you are asking for trouble.
That advice is sound almost everywhere. I still follow it in New York and New Jersey, where the permitting process is slow but predictable, and where the power grid is already there waiting for you. The sequence works because the variables behind it are stable. You know, roughly, what a permit will cost and how long it will take. You know the utility can supply what you need.
Cross into certain parts of Africa or into newer markets in Eastern Europe, and that same sequence can stall a project for years. Not because the people are less capable. Because one of the variables in the standard order isn’t stable at all: power.
Where the Order Breaks Down
In a mature market, energy is the easy part. You call the utility, you pay the connection fee, and you move on to financing and permits. In a market where the grid is still being built out, energy capacity might be the hardest and least certain part of the whole project. Treating it like step three on a checklist, after land and before permits, means you could spend two years on everything else only to find out the power isn’t there, or won’t be there for another five.
I learned this the hard way early in my work outside the US. I followed the order I’d always used. Land first, because that’s what you can see and touch. Then I started the slower process of asking what power supply actually looked like for that site. By the time I had a real answer, the financing terms I had lined up had changed, and so had some of the local relationships I was counting on.
What I Do Instead
Now, in any market where I’m not certain the grid can support the project, I flip the order. Energy capacity is the first question, not the third. I want to know what power exists on site today, what’s been promised, and who actually controls the timeline for anything beyond that. Only once I have a real answer do I move into land and financing conversations, because now I know what I’m financing against.
This isn’t a universal rule. It’s a rule for a specific condition: markets where the energy supply is the least predictable part of the project. If you’re building in a place where the grid is mature, flipping the order would just slow you down for no reason. The standard sequence exists because it’s efficient when every input is reasonably certain. The whole point is knowing which input, in your specific market, is not.
How to Tell Which Order You Need
A simple way to check: ask what would most likely blow up your timeline, and ask it before you commit to anything else. In some markets, that’s zoning. In others, it’s financing terms. In the markets I work in most now, it’s almost always energy. If the answer to “what’s the biggest unknown” changes, the order you build in should change with it.
I’d tell anyone newer to this work not to treat the standard sequence as a law. Treat it as a default that holds until one variable in your specific market is less certain than the others. When that happens, move that variable to the front, even if it feels like you’re doing things backward.
The Part People Miss
The mistake isn’t skipping steps. It’s running steps in an order that made sense somewhere else. A checklist built for one market, applied without adjustment to another, isn’t careful. It just looks careful. The discipline is in asking, every time, whether the order you’re used to still fits the ground you’re standing on.